Working method when using uncertainty criterion in PeriodOfUse

Uit informatiestandaarden
Ga naar: navigatie, zoeken

back to FD

back to page with additional documentation

If there is a situation-dependent startDateTime or endDateTime, this can be indicated in the data element PeriodOfUse.Condition. This condition makes explicit what the situation dependency entails. Examples of this are:

  • ‘Start X days before admission’ – if the exact start time depends on a planned hospital admission.
  • ‘Stop X days after holiday’ – if the medication is tapered off after a specific event with an uncertain end date.

See the page Examples uncertainty condition for details on how to use this condition.
In this section it is elaborated what this means for recording the MA.

Starting medication with uncertain startDateTime

Example: ‘start 3 days before admission’. It concerns medication for an indefinite duration. The date of admission becomes 10 August Three MAs are recorded.

Building block Description Completion
MA1 future MA for an indefinite duration PeriodOfUse.Criterion = 'start 3 days before admission'
startDateTime = leave empty
endDateTime = leave empty
duration = leave empty
date of admission known = 10 August
stop-MA (MA2) technical cancel-MA with stop type 'cancelled' PeriodOfUse.Criterion = leave empty
startDateTime = startDateTime of MA1 = leave empty
endDateTime = leave empty
duration = leave empty
RelatieMedicatieafspraak = MA1
MA3 modified MA for an indefinite duration, concrete completion of the startDateTime PeriodOfUse.Criterion = leave empty
startDateTime = 7 August
endDateTime = leave empty
duration = leave empty
RelatieMedicatieafspraak = MA1

Instead of leaving the startDateTime and endDateTime of the technical cancel-MA empty, the date of recording can also be entered for both. Because it concerns a cancel-MA both must be equal (see paragraph 5.2.2.3.2). MA1 must be regarded as a current MA. The startDateTime, endDateTime and duration are however all empty. The agreement is then to use the RegistrationDateTime as start of the MA.

Stopping medication with uncertain endDateTime

Example: ‘stop 1 week after end of vacation’. The vacation starts on 1 February. It is not yet known how long the vacation will last.

Building block Description Completion
MA1 original MA PeriodOfUse.Criterion = 'stop 1 week after end of vacation'
startDateTime = 1 February
endDateTime = leave empty
duration = leave empty
date of return from vacation known = 1 March
stop-MA (MA2) stop-MA with stop type 'stopped' PeriodOfUse.Criterion = not applicable
startDateTime = startDateTime of MA1 = 1 February
endDateTime = 8 March
duration = leave empty
RelatieMedicatieafspraak = MA1

Starting and stopping medication with uncertain period

Example: ‘start 1 day before vacation, stop 7 days after end of vacation’. It concerns an antimalarial during a stay in Laos of 20 days. The departure date is not yet known.

Building block Description Completion
MA1 future MA with duration of use of 28 days PeriodOfUse.Criterion = 'start 1 day before vacation, stop 7 days after end of vacation'
startDateTime = leave empty
endDateTime = leave empty
duration = 28 days
departure date known = 3 January
cancel-MA (MA2) technical stop-MA with stop type 'cancelled' termination of original MA with criterion PeriodOfUse.Criterion = leave empty
startDateTime = startDateTime of MA1 = leave empty
endDateTime = leave empty
duration = leave empty
RelatieMedicatieafspraak = MA1
MA (MA3) modified MA with duration of use of 28 days, concrete completion of the startDateTime PeriodOfUse.Criterion = leave empty
startDateTime = 2 January
endDateTime = leave empty
duration = 28 days
RelatieMedicatieafspraak = MA1

Instead of leaving the startDateTime and endDateTime of the technical cancel-MA empty, the date of recording can also be entered for both. Because it concerns a cancel-MA both must be equal (see paragraph 5.2.2.3.2). MA1 must be regarded as a current MA. The startDateTime, endDateTime and duration are however all empty. The agreement is then to use the RegistrationDateTime as start of the MA.

Interrupting medication with uncertain interruption period

Temporary interruption is stopping the medication for a certain period. Two new MAs are created within the same MBH:

  • A stop-MA with stop type ‘interrupted’, reference to the MA to be interrupted in RelatieMedicatieafspraak and reason for interruption in RedenWijzigenOfStaken.
  • A new MA for resumption with relation to that stop-MA and possibly the reason for resumption in RedenWijzigenOfStaken. This can be created immediately or later, for example only when the date of resumption is known.

If the exact moment of interruption is not yet known, endDateTime and duration of the interruption-MA cannot be completed. In PeriodOfUse.Criterion it is explained when the interruption must start. The startDateTime of the resumption-MA is then also not yet known.

For recording the resumption-MA two working methods are possible. Below this is elaborated using the example ‘stop 3 days before procedure and resume 1 day after procedure medication for an indefinite duration’. The original MA started on 1 January and the date of the procedure becomes 4 July.

Variant 1: record resumption-MA only when resumption date is known
In this variant no resumption-MA is created when recording the interruption. The date of the procedure is then not yet known. Only when that date is known is the resumption-MA recorded. The interruption-MA is then also concretely completed.

Building block Description Completion
MA1 MA for an indefinite duration PeriodOfUse.Criterion = leave empty
startDateTime = 1 January
endDateTime = leave empty
duration = leave empty
interruption-MA (MA2) stop-MA with stop type 'interrupted', moment of interruption and resumption recorded with criterion PeriodOfUse.Criterion = 'stop 3 days before procedure and resume 1 day after procedure'
startDateTime = startDateTime of MA1 = 1 January
endDateTime = do not complete
duration = do not complete
RelatieMedicatieafspraak = MA1
date of procedure known = 4 July
interruption-MA (MA3) new stop-MA with stop type 'interrupted', concrete completion of the moment of interruption PeriodOfUse.Criterion = do not complete
startDateTime = startDateTime of stop-MA (MA2) = 1 January
endDateTime = 1 July
duration = do not complete
RelatieMedicatieafspraak = MA2
resumption-MA (MA4) new MA for an indefinite duration, concrete completion of the moment of resumption PeriodOfUse.Criterion = do not complete
startDateTime = 5 July
endDateTime = do not complete
duration = do not complete
RelatieMedicatieafspraak = MA3

Variant 2: record resumption-MA immediately when interrupting
In this variant the resumption-MA is recorded at the same time as the interruption-MA. As soon as the exact moments are known, both the interruption-MA and the resumption-MA are concretely recorded. The previously recorded MAs with a criterion are then modified.

Building block Description Completion
MA1 MA for an indefinite duration PeriodOfUse.Criterion = leave empty
startDateTime = 1 January
endDateTime = leave empty
duration = leave empty
interruption-MA (MA2) stop-MA with stop type 'interrupted', moment of interruption recorded with criterion PeriodOfUse.Criterion = 'stop 3 days before procedure'
startDateTime = startDateTime of MA1 = 1 January
endDateTime = do not complete
duration = do not complete
RelatieMedicatieafspraak = MA1
date of procedure known = 4 July
resumption-MA (MA3) future-MA for an indefinite duration, moment of resumption recorded with criterion PeriodOfUse.Criterion = 'start 1 day after procedure'
startDateTime = leave empty
endDateTime = leave empty
duration = leave empty
RelatieMedicatieafspraak = MA2
date of procedure known = 4 July
interruption-MA (MA4) new stop-MA with stop type 'interrupted', concrete completion of the moment of interruption PeriodOfUse.Criterion = leave empty
startDateTime = startDateTime of stop-MA (MA2) = 1 January
endDateTime = 1 July
duration = leave empty
RelatieMedicatieafspraak = MA2
cancel-MA (MA5) technical stop-MA with stop type 'cancelled', termination of the resumption-MA with criterion PeriodOfUse.Criterion = leave empty
startDateTime = startDateTime of resumption-MA (3) = leave empty
endDateTime = leave empty
duration = leave empty
RelatieMedicatieafspraak = MA3
resumption-MA (MA6) modified future MA for an indefinite duration, concrete completion of the moment of resumption PeriodOfUse.Criterion = leave empty
startDateTime = 5 July
endDateTime = leave empty
duration = leave empty
RelatieMedicatieafspraak = MA3

Instead of leaving the startDateTime and endDateTime of the technical cancel-MA empty, the date of recording can also be entered for both. Because it concerns a cancel-MA both must be equal (see paragraph 5.2.2.3.2). MA1 must be regarded as a current MA. The startDateTime, endDateTime and duration are however all empty. The agreement is then to use the RegistrationDateTime as start of the MA.

↑ Back to top

Document history

Version Date Description
9 3.0.0-rc.2 February 2026 for all changes see: *Releasenotes